Iljin Electric disclosed the deal on the Korea Exchange on 19 November; the contract was signed on 18 November. Besides making and supplying the extra-high-voltage cables, the company will also build the underground transmission line.
Key terms:
- Contract: supply and installation of 230kV power cables, auxiliary cables and accessories (NDC453)
- Value: about S$108.27 million (around KRW 112.5 billion)
- Period: 18 November 2026 to 30 December 2030
- Payment: no deposit or advance; billed as supply progresses
According to Korean media, the line will power an advanced industrial estate near Changi Airport. The route runs through an area dense with industrial facilities and infrastructure, so the underground works are technically demanding.
This is Iljin Electric's second Singapore cable order above KRW 100 billion this year. In May it signed a similar contract worth about KRW 108.6 billion, bringing its Singapore orders this year to roughly KRW 221.1 billion.
What it means for the industry
Singapore's grid build-out keeps gathering pace: after Taihan's 400kV award this month, another Korean cable maker has joined in. Local civil, trenching and traffic-diversion subcontractors may find cable-trench work around Changi.