The mall will close on 31 March 2027. SingLand considered phased works but chose a full closure to avoid prolonged noise and disruption; the three hotels next to it will stay open throughout.
Key numbers
- Gross floor area: from 315,046 sq m to about 362,493 sq m
- Three new towers: homes, serviced apartments, a hotel and Grade A offices
- Mall net lettable area: from just under 800,000 sq ft to slightly below 500,000 sq ft
- Completion: 2031, stabilising in 2032 or 2033
In a group interview on 13 November, CEO Jonathan Eu said the smaller mall frees floor area for other uses, with residents, office workers and hotel guests expected to drive traffic.
The fourth-storey rooftop, now used for mechanical equipment, will house racquet courts and a clubhouse. A sheltered public space of about 40,000 sq ft could host tournaments one day and live music the next.
Background
Marina Square opened on reclaimed land in 1986. SingLand finished upgrading Singapore Land Tower and West Mall in 2025, and the 35-storey The Clifford is due for completion in 2028.
What it means for the industry
A major city-centre mall is moving towards redevelopment, involving demolition, tower construction beside operating hotels and M&E works. Main contractors, demolition and M&E subcontractors should watch for the coming tenders.