Hong Leong Building Revamp Keeps 95% of Structure

AI-generated illustration
Summary

Hong Leong Holdings has completed the revamp of its 45-storey Hong Leong Building, part of a programme with digital integration costing over S$40 million.

The 158m CBD office tower was among Singapore's tallest buildings when it opened in 1976. Works began in October 2023 and were completed in September this year.

The project kept the original structure and granite facade, refurbished the street-facing podium, and upgraded common areas and lift lobbies. A new sheltered drop-off on Level 5 replaces the old one along Telegraph Street.

Project facts

  • Height: 45 storeys, 158m
  • Works: October 2023 to September 2026
  • Structure retained: about 95%
  • Certification: BCA Green Mark Platinum

The company said keeping the existing structure significantly cut material waste and the environmental impact of the works.

In parallel, it worked with PwC Singapore and technology partners Showsuite, SAP and Planon Asia to put sales, leasing and finance for its residential and commercial businesses on one platform. It says data accuracy improved by 30% and operational efficiency by up to 65%.

What it means for the industry

Older CBD office towers are being refreshed one by one. Asset enhancement that retains the structure while renewing facades and common areas gives fit-out, facade and M&E contractors steady work, and makes green certification easier to achieve.

Report

To complete the feature you choose, the related content is sent to our third-party AI provider, OpenAI, and may be processed outside Singapore.

  • May be sent: text you enter, photos, chat messages, quote details and resume text.
  • Phone numbers, emails and ID numbers in text are masked first. Photos are not, so avoid uploading sensitive material.
  • You can use the platform without these AI features, and change this any time in Data & privacy.
Read the Privacy Policy