National Development Minister Chee Hong Tat announced the changes at REDAS's 67th anniversary dinner. URA issued circular DC26-12 the same day, with immediate effect.
What changes for GFA
- Roof eaves and sun-shading devices: exempt depth raised from 2m to 3m; they must be column-free and inaccessible except for maintenance
- Covered linkways: no longer need to sit within a landscaped area to be exempt, though greenery requirements such as landscape replacement areas still apply
- Basement M&E spaces: exemption to extend from basement carpark floors to all basement floors, with details to come
Owners of non-conserved buildings generally no longer need URA planning permission to add compliant eaves or sun-shading devices. Conserved buildings still do.
Green retrofit funding
BCA's Green Mark Incentive Scheme for Existing Buildings 2.0 (GMIS-EB 2.0) has also been enhanced. Targeted upgrades such as chiller plant replacement can now be funded without full Green Mark certification, as long as energy-efficiency standards are met.
- Coverage widened to structural roof strengthening for solar panels and alternative cooling technologies
- Hybrid cooling (air-conditioning set up to 27°C with fans) qualifies for 50% co-funding, capped at S$200,000
- Application window extended from 31 March 2027 to 31 March 2030
- Average payback for efficiency retrofits expected to shorten by about two years
What it means for the industry
Architects and developers can design more generous shade and rain shelter without giving up buildable area. For contractors, add-on eaves and linkways plus chiller, solar and roof-strengthening retrofits should mean more small and mid-sized upgrading jobs.